Do I Need a Phase 3 Remediation Strategy? (And What Is It?)

When a Phase 2 Site Investigation identifies contamination that could pose a risk to human health, groundwater, or property, the next logical step is to assess whether a Phase 3 Remediation Strategy is required.

Not every site will need remediation, but where contamination has been identified that exceeds acceptable thresholds — and crucially, where someone (human health) or something (surface water, groundwater or ecology) could be at risk — planning authorities and regulators expect a clear, practical plan to manage the risks.

This article explains when a Phase 3 is necessary, what a Remediation Strategy involves, and how Clear Environmental ensures that remediation is commercially proportionate, technically robust, and focused on achieving regulatory approval without unnecessary complexity.

When is a Phase 3 Remediation Strategy Required?

A Phase 3 Remediation Strategy is needed when:

  • Contaminants exceed assessment criteria for human health, groundwater, or property and source–pathway–receptor linkages are confirmed that could result in unacceptable risks;
  • Planning conditions require a strategy to demonstrate that risks can be effectively mitigated.

Typical scenarios that trigger a Phase 3 include:

  • Heavy metals, hydrocarbons, or asbestos identified at concentrations above acceptable screening levels and with the potential to impact receptors;
  • Ground gases (such as methane or carbon dioxide) recorded at concentrations requiring protection measures;
  • Groundwater impacts where contaminants could migrate to sensitive receptors such as aquifers or surface waters.

In short, if risks cannot be adequately managed by design changes or minor mitigation alone, a structured Remediation Strategy will be necessary.

What is a Remediation Strategy?

A Remediation Strategy is a formal plan that:

  • Identifies the contamination issues requiring management;
  • Sets clear remediation objectives;
  • Selects appropriate remediation methods based on technical, sustainability, and commercial factors;
  • Outlines how the success of remediation will be verified and documented.

The objective is to ensure that, once the remediation measures are completed, the site will be suitable for its intended future use without posing unacceptable risks.

Clear Environmental’s Remediation Strategies are designed to be clear, practical, and regulator-focused — ensuring swift approval while protecting your project’s timeline and financial viability.

How Are Remediation Options Selected?

Remediation options are evaluated through an Options Appraisal process, which considers:

  • Technical effectiveness in breaking pollutant linkages;
  • Commercial feasibility, including construction programme impact;
  • Environmental sustainability, including waste minimisation;
  • Health and safety during implementation.

We follow the approach outlined by the Environment Agency’s Land Contamination Risk Management (LCRM) framework (Stage 2 and Stage 3), ensuring that selected remediation methods are proportionate to the risks identified.

For example:

  • Localised hotspots may be addressed through targeted excavation. In some circumstances, the contaminants may be suitable to be placed beneath areas of hardstanding or building footprint — minimising offsite disposal and therefore developer costs. If material can be kept on site and reused, it promotes sustainability as well;
  • Ground gas risks may require the installation of passive or active venting systems. For the vast majority of sites where gas protection is required, a passive venting system (residential) or suitable floor slab (commercial) in conjunction with a membrane will form a practical gas remediation solution;
  • Widespread contamination might be better managed through a capping system in soft landscaping (generally 450mm, but this varies between local authorities). Where groundwater remediation is required, long-term monitoring may be needed to satisfy regulatory requirements and confirm the effectiveness of the remedial efforts.

Selecting the correct solution early avoids unnecessary expenditure and delays during later stages of development.

How Remediation Reduces Risk

When developing a Remediation Strategy, there are three broad approaches to reducing environmental risk:

1. Source Removal or Reduction

Removing or reducing the mass or concentration of contaminants at the source is often the most direct method of risk mitigation.

This could involve excavating contaminated soils, treating contaminated groundwater, or using chemical, biological, or physical methods to stabilise or destroy contaminants.

Where possible, material reuse and sustainable remediation practices are considered to minimise disposal costs and reduce environmental impacts — critical in light of rising landfill taxes and regulatory pressures.

2. Pathway Management

Sometimes, it is more practical to interrupt the route by which contamination reaches a receptor.

Common examples include installing engineered barriers (e.g., gas membranes, capping layers), modifying ground conditions to alter groundwater flow, or adjusting the site layout to remove sensitive uses from impacted areas.

Pathway management often provides a highly effective and commercially efficient method of reducing risk without major disturbance.

3. Receptor Removal

In some cases, managing risk may involve restricting or removing the receptor itself.

This could include restricting access to contaminated areas, preventing the use of affected groundwater, or altering the intended site use to one with lower sensitivity.

While complete receptor removal is not always feasible, selective controls and use of protective measures are often effective in reducing overall site risks.

Clear Environmental considers all three approaches when preparing remediation strategies — selecting the most appropriate, proportionate method based on site-specific risks and project objectives.

What Does a Remediation Strategy Typically Contain?

A Remediation Strategy prepared by Clear Environmental will usually include:

  • Summary of Phase 2 findings: Clear identification of contamination and associated risks;
  • Remediation objectives: Specific outcomes required to mitigate risks;
  • Description of selected remediation methods: Justification for the chosen approach based on effectiveness, cost, and sustainability;
  • Implementation methodology: Practical delivery plan and health and safety considerations;
  • Verification strategy: Plan for post-remediation sampling, monitoring, and reporting to demonstrate compliance;
  • Contingency planning: Approach for addressing unexpected contamination encountered during works.

This structure ensures that the Remediation Strategy is aligned with planning requirements, regulator expectations, and commercial project drivers.

Managing Remediation Expectations

It is important to emphasise that not all remediation needs to be complex or disruptive.

In many cases:

  • Localised contamination can be managed through limited soil removal and disposal or relocation on site;
  • Risks can be mitigated by simple design solutions, such as installing gas protection measures.

Clear Environmental’s approach is to scale remediation precisely to the risks identified — ensuring that your development progresses efficiently without unnecessary abnormal costs.

Where remediation requirements are more significant, early clear advice allows for accurate cost forecasting and programme integration.

Frequently Asked Questions

Do I always need a Phase 3 if contamination is found?

No. If the Phase 2 assessment confirms that risks are low or that there are no complete pollutant linkages, remediation may not be required.

How long does it take to agree a Remediation Strategy?

Typically, Remediation Strategies are prepared and agreed within 2–4 weeks, depending on site complexity and regulator response times.

Can remediation works be scheduled alongside development?

Yes. Where possible, remediation is integrated into enabling works or early construction stages to minimise programme impact.

Conclusion: Structured, Commercially-Focused Remediation

A Phase 3 Remediation Strategy is a critical step when contamination risks are confirmed.

Handled correctly, it provides certainty for planners, investors, and project teams — allowing development to proceed safely and sustainably.

Clear Environmental’s remediation strategies are tailored to each site’s unique risks and commercial drivers, ensuring that remediation is proportional, practical, and aligned to development goals.

Related Services

When a Phase 1 Desk Study identifies potential environmental risks, the next step is a Phase 2 Site Investigation — also called an intrusive investigation. This critical stage gathers real-world data to confirm or rule out contamination, protecting your project from unforeseen costs, planning delays, or environmental liabilities.

In this guide, we break down:

  • How Phase 2 builds on Phase 1.
  • The different investigation techniques (and when to use each).
  • Typical timescales.
  • How laboratory testing refines the site’s risk profile.
  • What to expect at the end of a Phase 2 investigation.

How Phase 2 Builds on Phase 1

While a Phase 1 is based on desk research and a site walkover, a Phase 2 collects physical evidence through soil, groundwater, and ground gas sampling.


In short:

Phase 1 = Identify Potential Risks.

Phase 2 = Confirm or Dismiss Risks with Hard Data.

The findings from Phase 2 enable:

  • Quantitative Risk Assessments (QRA) based on actual contamination levels.
  • Decisions about whether remediation is necessary.
  • Planning condition discharge if no unacceptable risks are found.

Phase 2 Site Investigation Methods

Different methods are used depending on the site, the anticipated risks, and the required depth of investigation:

  • Trial Pits:
    • Best For: Shallow contamination, made ground assessment, visual soil profiling, locating foundations.
    • Typical Depths: Up to 4 metres.
    • Equipment: Mechanical excavator or hand-dug.
    Borehole (Window Sampling):
    • Best For: Shallow contamination, installation of ground gas and groundwater wells, restricted access sites, cost-effective sampling.
    • Typical Depths: Generally 5–6 metres, but can extend up to 10 metres depending on ground conditions.
    • Equipment: Window sampling rig (tracked or towed).
  • Boreholes (Cable Percussive):
    • Best For: Deeper soils, groundwater sampling, ground gas monitoring, and collecting geotechnical data.
    • Typical Depths: Up to 30 metres or more.
    • Equipment: Cable percussion drilling rig.
  • Boreholes (Rotary Drilling):
    • Best For: Hard ground, bedrock investigations, and installation of deep groundwater wells.
    • Typical Depths: Up to 100 metres or more.
    • Equipment: Rotary drilling rig (open hole, cored, or augered).
  • Method
    Best For
    Typical Depths
    Equipment
    Trial Pits
    Shallow contamination, made ground, visual soil profiling, locating foundations
    Up to 4m
    Mechanical excavator or hand-dug
    Borehole (Window Sampling)
    Shallow contamination, installation of ground gas and groundwater wells, restricted access sites, cost-effective sampling
    Generally 5-6m but can go up to 10m depending on ground conditions
    Window sampling rig (tracked or towed)
    Boreholes (Cable Percussive)
    Deeper soil investigation (or dense gravels), groundwater sampling, ground gas monitoring, geotechnical data, restricted access if cut down.
    Up to 30m+
    Cable percussion drilling rig
    Boreholes (Rotary)
    Competent geology (hard), bedrock investigations, proper recovery of chalk, deep groundwater wells
    Up to 100m+
    Rotary drilling rig (open hole, cored, or augered)
    Tip: On smaller development sites, a combination of trial pits and window sampling often provides excellent coverage at a cost-effective price.

    Types of Laboratory Testing During Phase 2

    After sampling, the materials collected are sent for laboratory analysis to determine contamination levels:

    • Soil Testing:
      • Heavy metals (e.g., lead, arsenic)
      • Hydrocarbons (TPH, PAHs)
      • Asbestos in soil
      • Emerging contaminants (e.g., PFAS)

    • Groundwater Testing:
      • Soluble contaminants (e.g., hydrocarbons, BTEX, solvents)
      • Metals in solution
      • PFAS detection

    • Ground Gas Monitoring:
      • Methane, carbon dioxide, oxygen concentrations
      • Flow rates (for CS classification)

    The results are then compared against appropriate assessment criteria (e.g., GACs/SACs) to determine whether remediation is needed.

    What Happens After Phase 2 Sampling?

    1. Data Analysis and Quantitative Risk Assessment (QRA):

    Risk to human health, controlled waters, or property assessed.

    2. Conceptual Site Model Update:

    Confirmed pollutant linkages mapped and risk-ranked.

    3. Decision Point:

    No significant risks: Reporting and planning condition discharge.

    Significant risks: Recommend remediation (Phase 3).

    Phase 1 vs Phase 2 - Quick Comparison Table

    Feature
    Phase 1 (Desk Study)
    Phase 2 (Site Investigation)
    Based On
    Desk research and site Walkover
    Sampling and laboratory testing
    Purpose
    Identify potential contamination risks and determine if further investigation is requried
    Confirm or rule out presence of contamination
    Outcome
    Initial risk screening, inform scope of Phase 2 (if requried)
    Quantitative risk assessment
    Typical Timescales
    10 Days
    4-6 Weeks

    FAQs About Phase 2 Site Investigations

    What happens if contamination is found in a Phase 2?

    More Than

    If contaminants exceed safe levels, a Remediation Strategy (Phase 3) will be needed to outline how risks will be managed.

    Can a Site Investigations rule out the need for remediation?

    More Than

    Yes — many sites require no further action after a properly scoped Phase 2 investigation.

    Is ground gas monitoring always required during a Phase 2?

    More Than

    Not always. It depends on the site's history, geology, and desk study findings.

    Why a Clear Phase 2 Strategy Matters

    A well-designed Phase 2 Site Investigation provides confidence, clarity, and control.


    It ensures you're fully informed about site risks, avoids unnecessary remediation, and moves your project efficiently through planning.

    At Clear Environmental, we tailor Phase 2 investigations to your site — no over-scoping, no hidden costs, just clear advice.

    If your Phase 2 results raise concerns, understanding how to move forward with proportional, commercially realistic remediation is crucial.

    To learn what happens next from Phase 2 to Remediation Click Here.

    Related Services

    What is a Phase 1 Desk Study (Preliminary Risk Assessment)?

    A Phase 1 Desk Study (Preliminary Risk Assessment) is an initial environmental assessment that researches a site’s history and conditions to identify potential contamination risks.

    Whether you're planning to develop land, submit a planning application, or purchase a brownfield site, understanding environmental risks early is essential.


    A Phase 1 Desk Study — also called a Preliminary Risk Assessment — is the first critical step in managing those risks efficiently, helping avoid costly surprises later in your project.

    This guide explains exactly what a Phase 1 involves, why it’s required, and what you can expect from the process.

    What is a Phase 1 Desk Study?

    A Phase 1 Desk Study is a preliminary environmental assessment that evaluates the potential for land contamination based on historical and current land uses.

    It is called a “desk study” because it mainly relies on reviewing existing records and data sources, alongside a site visit.


    It does not involve any intrusive ground investigation — that's reserved for Phase 2 if risks are identified.

    In simple terms:

    A Phase 1 identifies if there’s a potential problem — before you commit to site purchase, design, or construction.

    Why is a Phase 1 Desk Study Needed?

    A Phase 1 is often required to:

    • Support planning applications (especially brownfield or previously developed sites).
    • Satisfy lender due diligence for property transactions.
    • Manage liability and avoid unexpected abnormal costs.
    • Confirm if further investigations (Phase 2) are needed.

    Without a Phase 1, local authorities, insurers, and funders may refuse to progress development or financing.

    Key Components of a Phase 1 Desk Study

    A thorough Phase 1 typically includes:

    Component
    What it Involves
    Desk Based Research
    Reviewing historical maps, regulatory databases, geological records, flood risks, landfill sites, industrial use, and environmental permits.
    Site Walkover Survey
    Visiting the site to observe current land use, conditions, structures, evidence of contamination (e.g., oil staining, storage tanks).
    Conceptual Site Model (CSM)
    Developing a model showing potential contamination sources, pathways (e.g., groundwater movement), and receptors (humans, buildings, water).
    Risk Assessment
    Identifying pollutant linkages and advising whether a Phase 2 investigation is necessary.

    What Does a Phase 1 Report Contain?

    A typical Phase 1 Desk Study Report will include:

    • Executive Summary (key findings and recommendations).
    • Site location and description.
    • Historical land use review (maps and aerial photography).
    • Environmental setting (geology, hydrology, groundwater).
    • Regulatory database review (permits, enforcement notices, pollution incidents).
    • Walkover survey findings (including annotated site photos).
    • Preliminary Conceptual Site Model (CSM).
    • Risk assessment and clear conclusions.
    • Next steps, if further investigation is needed.

    At Clear Environmental, our Phase 1 reports are concise, commercially-focused, and designed to satisfy planning authorities and lenders without unnecessary complexity.

    How Long Does a Phase 1 Desk Study Take?

    Most Phase 1 assessments can be completed within 10 Days.


    We also offer fast-track services if you’re working to tight planning or transaction deadlines.

    Phase 1 Desk Study vs. Environmental Search: What's the Difference?

    Feature
    Phase 1 Desk Study
    Environmental Search Report
    Who prepares it?
    Environmental Consultant
    Data Aggregator (automated process)
    Site Walkover?
    Yes
    No
    Conceptual Site Model?
    Yes
    No
    Risk Assessment?
    Yes, taylored to your site, proposal and project
    No, generic alerts only
    Planning Authority Acceptance?
    Yes
    No
    Typical Cost
    £1,250+
    £200 - £400

    Key point: An Environmental Search is not a substitute for a Phase 1 — it’s simply a basic desktop screening.

    Why Clear Environmental for Your Phase 1?

    A Phase 1 Desk Study isn’t just a box-ticking exercise — it’s your first opportunity to manage risks, reduce abnormal development costs, and protect your investment.

    At Clear Environmental, we combine technical expertise with commercial insight to deliver Phase 1 Reports that meet planning, legal, and financial requirements — quickly and clearly.

    Related Services

    FAQs About Phase 1 Environmental Desk Studies

    When should I commission a Phase 1 Environmental Report?

    More Than

    Ideally before site acquisition or at the earliest planning stage, so risks and costs are identified early.

    Will a Phase 1 Desk Study always recommend a Phase 2 Site Investigation?

    More Than

    No — many sites with clean histories and no risk linkages can be signed off at Phase 1.

    Who needs a Phase 1 Environmental Desk Study?

    More Than

    Developers, property investors, planners, architects, solicitors, and lenders commonly require Phase 1 studies.

    Will the council accept my Phase 1 report for planning?

    More Than

    Yes — provided it follows UK guidance (such as EA Land Contamination Risk Management (LCRM)) and is prepared by qualified specialists.

    What happens if my Phase 1 shows contamination risks?

    More Than

    We’ll outline the recommended Phase 2 site investigation scope and cost early, so you remain in control.

    FAQs About Contaminated Land Assessments

    What is a contaminated land assessment?

    More Than

    A contaminated land assessment identifies whether land poses environmental or health risks, helping manage liabilities before development or purchase.

    What is the difference between Phase 1 and Phase 2?

    More Than

    Phase 1 is a desktop and site walkover study identifies potential risks. Phase 2 collects soil, water, and gas samples to confirm actual contamination.

    How long does a Phase 1 Environmental Report and Phase 2 Site Investigation take?

    More Than

    A Phase 1 takes 10 days. A Phase 2 takes 4-6 weeks depending on complexity.

    What happens if contamination is found during a Site Investigation?

    More Than

    A remediation strategy is developed to remove or manage the risks to acceptable levels.

    Do I always need a Phase 2 investigation?

    More Than

    Not always — if Phase 1 finds no significant risks, Phase 2 may not be necessary.

    Category
    Blog and articles

    Latest insights and trends