Ground information the design team can actually use.

Ground investigation should provide the information needed for design decisions, not simply produce another report. We target the parameters, locations and uncertainties that could change the foundation, slab, pavement or construction strategy.

Geotechnical site investigation drilling rig in Sevenoaks, Kent
Typical turnaround
1–6 weeks

Foundation exposures reported within a week; full investigations to programme.

01 / What it tells you

Will the foundations work?

The ground model, groundwater regime and design parameters your structural engineer needs.

02 / What it helps you decide

Shallow foundations, piles or ground improvement

And the parameters for each, before detailed design depends on them.

03 / You receive

Factual and interpretive geotechnical report

With design recommendations for structural and civil engineers, architects and contractors.

Why it matters

Resolve the ground-risk uncertainties before detailed design depends on them.

Testing the soil and rock so your engineer can design foundations that are safe, without over-designing them.

Typical triggers include designing foundations for new buildings or extensions, assessing whether shallow foundations are viable or piling is needed, designing car parks and access roads, reusing existing structures and checking for aggressive ground affecting buried concrete.

How we approach it

From brief to answer.

Evidence the design team can use for foundation, slab and pavement decisions.

01

Plan

Investigation methods matched to the structure, loads and likely ground model, agreed with the design team.

02

Investigate

Window sampling, cable percussion and rotary drilling, trial pits, foundation exposures and probe holes.

03

Test

In-situ testing and laboratory classification, strength, compressibility, CBR and chemical testing.

04

Interpret

Ground model, groundwater regime and design parameters, with practical foundation and pavement recommendations.

Where it can lead

Three honest outcomes.

We report what the evidence supports. Each outcome is a legitimate answer, and the first is often the most valuable.

Outcome A

Shallow foundations viable

Bearing strata and allowable pressures defined for design.

Outcome B

Alternative foundations needed

A clear basis for piling or ground improvement before detailed design.

Outcome C

Existing structures recorded

Footing and slab dimensions, depth and condition captured for the structural model.

What you get

Design-ready ground information.

Plain-English conclusions up front, with the technical detail regulators and engineers need behind them.

✓
Exploratory hole and trial pit logs with photographs
✓
In-situ and laboratory test results
✓
Foundation, floor slab and pavement design recommendations
✓
Buried concrete classification, groundwater observations and implications for construction

Guidance we work to: BS 5930, Eurocode 7 (BS EN 1997) and BRE Special Digest 1.

In practice

A recent project.

What this looked like on a real site, and what the client could do as a result.

Geotechnical site investigation fieldwork in Sevenoaks, Kent
Commercial redevelopment / Sevenoaks

Finding the foundation constraint before detailed design.

For a proposed commercial redevelopment in Sevenoaks, Clear investigated shallow and deeper ground conditions and established that conventional shallow foundations were not an appropriate basis for the building. The project team could then focus detailed design on deeper foundations, piling or ground improvement, with site-specific information also provided for pavement design.

Read the case study →
Questions

Common questions.

Can you investigate existing foundations?

Yes. We hand-dig trial pits and probe holes to expose existing footings and slabs, recording type, depth, dimensions and condition, and tagging each location for the structural engineer.

Do you provide pavement design information?

Yes. We provide site-specific information, including CBR values, so car parks, yards and access roads are designed on real ground conditions.

Get a quote for your site.

Send us the address and what you’re planning. A senior consultant will reply with a quote and the right first step, usually within one working day.

✓ Free, with no obligation
✓ You don’t need to know which service you need
✓ Reviewed by a senior consultant
E hello@clearenviro.co.uk